Date: June 10, 2009
EmpowHR will begin using the same naming standard for releases as PPS, calendar-year (CY) and pay-period (PP). Release 2 will now be called CY09 PP13.
Software Change Request (SCR) 80175 has been rescheduled for testing and implementation with the SCRs scheduled for PP 13. The chart below identifies the Software Change Requests for Release CY09 PP12 of EmpowHR 9.0.
| SCR |
SCR Description |
Implementation Pay Period (PP) |
| 80175 |
NEWSINQ - New SINQ File Layout |
PP13 |
| 80281 |
DHS/HQ Award Data Link (Updated) |
PP13 |
| 80365 |
Automated Label for Sensitive Reports (Updated) |
PP13 |
| 90140 |
EmpowHR Import Modifications |
PP13 |
| 90141 |
EmpowHR 125 Document Mod |
PP13 |
| 90142 |
Position and PAR Discrepancies |
PP13 |
| 90195 |
Country of Citizenship - NEIS |
PP13 |
| 90196 |
Country of Citizenship – EmpowHR |
PP13 |
| DHS-052 |
TOPS IP# as NFC IP# |
PP13 |
| DHS-056 |
Job Code Page MR Number |
PP13 |
| DHS-112 |
Build Positions using Job Code |
PP13 |
Key Dates
April 27 - May 15: QAT
May 15: Provide Test Plan (80175 test plan provided April 24)
May 15: Provide QAT Test Results Summary Report
May 18: UAT Kickoff meeting
May 18 – June 24: UAT
June 23: UAT Test Results Summary Report
June 24: Go/No Go Decision
June 27 -28: Production Implementation
Information for all SCRs
- UAT PPS IDMS Database: IDMS61, CLIST EPAY
- UAT EPIC environment: EPIC EPAY UAT
- Data in the UAT environment is the same (no refresh was done)
- Processing Pay Period: same as production
- EmpowHR Export Times: 11:30 a.m. and 4:30 p.m. ET daily M-F
- PINE Pass Execution Time: 12:30 p.m. and 6:15 p.m. ET daily M-F
- EmpowHR Import Time: 1:30 p.m. and 2:30 a.m. ET daily M-F
|